1. List the emergency plan of hidden dangers and dangerous points, establish the registration system of entering the power station, and improve the evaluation system of the power station. (Emergency plan and system have been established and perfected)
2. The marking plate on the pipeline between the gas pump house and the power station is not clear. (Re-customized sign and posted)
3, gas generators using 400V low-voltage grid-connected, need to develop special measures to standardize grid-connected operation. (Developed and made for wall hanging)
4, involving the manufacturer's problems, reflected by the installation side to the manufacturer, come up with specific treatment suggestions. (The problem has been copied and reported to the manufacturer)
5. The smoke exhaust pipe has no insulation measures, and the detonation device is located in the generator room. Isolation measures and warning signs should be taken outside the room. (Exhaust 6, flue heat insulation measures have been completed, explosion-discharge device has been contacted by the manufacturer must be issued by the manufacturer rectification plan and implementation)
7, the gas power station should be included in the scope of safety inspection of the Shuileng mine, the Shuileng mine should carry out safety inspection and evaluation on a regular basis, and the inspection content should be reported to the power supply Department and the safety supervision Bureau.